16 December
๐—ง๐—ต๐—ถ๐˜€ ๐˜€๐˜๐—ผ๐—ฟ๐˜† ๐—ผ๐—ฟ๐—ถ๐—ด๐—ถ๐—ป๐—ฎ๐—น๐—น๐˜† ๐—ฎ๐—ถ๐—ฟ๐—ฒ๐—ฑ ๐—ผ๐—ป ๐Ÿฎ๐Ÿญ ๐—ก๐—ผ๐˜ƒ๐—ฒ๐—บ๐—ฏ๐—ฒ๐—ฟ ๐Ÿฎ๐Ÿฌ๐Ÿฎ๐Ÿญ. It took Eskom six years and R8 billion to construct a railway line to one of its largest power stations, Majuba in Mpumalanga. But the lineโ€ฏhas never been used and now vandalism and alleged sabotage have rendered it unusable. So, why does Eskom claim the problems at Majuba have been resolved?โ€ฏ